3. Project Timeline


Site clearance and demolition works for construction of the new Falkland Pavilion and the new Bowlers Arms began on Monday 17th September 2018. Building works are scheduled to start on Monday 1st October and to be completed by New Year 2020. This is the first visible sign of two years of hard work by members of the Club to get to this point.

Start Date: 17/09/18
Preparatory works: 17/09/18
Foundation works: 09/10/18
Groundworks up to GF Slab: 26/10/18
Superstructure: 03/12/18
Roof: 04/04/19
Internal works, M&E: 17/06/19
Decorating and fit out: 04/11/19
External work and car park extension: 12/06/19
Clear site and handover: 21/06/19
Finish date: 19/12/19